Friday, November 9, 2012

All formulas for PMP Exam

Q U A L I T Y
-------------
CoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 %


PERT = O + 4ML + P
--------------
6
MEAN -> Average


MODE -> The "most found" number


RANGE -> Largest - Smallest Measure.


MEDIUM -> No in the middle or avg. of 2 middle Nos


STD. DEV. OF TASK = P - O
____________
6


TASK VAR. = (P - O) 2 = Std. Dev ^ 2
____________
6
_____________
CP STD. DEV. = √ σ² + σ² + σ²


SIGMA 1 = 68.26
2 = 95.46
3 = 99.73
6 = 99.99




Channels of Communication
-------------------------
COMM = (N2 - N) / 2 = (N x (N - 1)) / 2




P R O J E C T S E L E C T I O N
---------------------------------
PV = F V .
-------
(1+r)ⁿ


FV = PV x (1+r)


NPV = S ( PV + PV + PV + PV )
---- ---- ---- ----
(1+r)ⁿ (1+r)ⁿ (1+r)ⁿ (1+r)ⁿ


Cash Flow = Cash Inflow - Cash Outflow


Discounted Cash Flow = CF x Discount Factor


ARR = S Cash Flow / No. of Years


ROI = (ARR / Investment) * 100 %


BCR = Benefits / Cost


Exp. Value = Probability % x Consequence $




Class of Estimates
-------------------
Definitive +5%


Capital Cost +10-15%


Appropriation +15-25%


Feasibility +25-35%


Order of Magnitude > +35%




Contract Incentives
--------------------
Savings = Target Cost - Actual Cost


Bonus = Savings x Percentage


Contract Cost = Bonus + Fees


Total Cost = Actual Cost + Contract Cost




E A R N E D V A L U E A N A L Y S I S
---------------------------------------------
PV (Present Value) = BCWS (Budgeted Cost of Work Schedule)


EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)


AC (Actual Cost) = ACWP (Actual Cost of Work Performed)


CV = EV - AC


CPI = EV / AC (efficiency)


SV = EV - PV


SPI = EV / PV


ETC = BAC - EV or (BAC - EV) / CPI


EAC = AC + ETC


EAC = BAC / CPI


VAC = BAC - EAC


% COMPLETE = EV / BAC x 100


% SPENT = AC / BAC x 100


CV% = CV / EV x 100


SV% = SV / PV x 100


The following are extracted from "PMP Resources":

The PMP exam is big on terminology. These are the basic Earned Value Terms you need to know. If you are studying to pass the PMP exam you should know these by heart and be able to derive them in case you are heartbroken. They really are fairly simple. In order from first to last:

BAC = Budget at Completion (Project budget)
AC = Actual Cost of the Work Performed
EV = Earned Value
EV = Budgeted Cost of the Work Performed
EV = % complete times BAC
PV = Planned Value
PV = Budgeted Cost of the Work Scheduled
CV = Cost Variance
CV = EV - AC
CPI = Cost Performance Index
CPI = EV/AC
SV = Schedule Variance
SV = EV - PV
SPI = Schedule Performance Index
SPI = EV/PV
EAC = Estimate at Completion
EAC = BAC/CPI
ETC = Estimate to Complete
ETC = EAC - AC
VAC = Variance at Completion
VAC = BAC - EAC